Venice Dual Force Main Project Status and Schedule

CURRENT STATUS

The project began in early Spring 2017 and construction completion is expected in Summer 2020.
Staging and other pre-construction activity will occur through June 2017 at the following shaft locations:

  • Shaft #4 – Pacific Avenue at 62nd Avenue
  • Shaft #5 – Via Marina at Ballona Creek
  • Shaft #10 – Marquesas Way at Via Dolce
  • Shaft #11 – Hurricane Street at Canal Court

Construction activities, including shaft excavation and underground micro tunneling, will begin in late June 2017 at the following shaft locations:

  • Shaft #10 – Marquesas Way at Via Dolce
  • Shaft #11 – Hurricane Street at Canal Court

Additional information on the above noted pre-construction and construction activity, including maps, traffic diversions and parking restrictions as well as other activities can be found here:
Construction notice Shaft #4
Construction notice Shaft #5
Construction notice Shaft #10
Construction notice Shaft #11

Expected construction hours are as follows:
City of Los Angeles: Mon – Fri, 7am – 7pm; Saturdays as needed, 8am – 6pm.
County of Los Angeles: Mon – Friday, 8am – 5pm; Saturdays as needed, 8am – 5pm.

Night work, if required, will be from 7pm to 7am with advance notice in the City and the County.

As the project progresses, additional updates will be posted.